Projects & Collections
Major project financial health, billing, and collection tracking
AI Insights & Action Plan
CFO-grade analysis of Projects & Collections — powered by Lovable AI
Total Contract Value
1,445
SAR M
Total Collected
615
SAR M
Unbilled Progress
195
SAR M
High Risk Projects
2
of 6 total
Project Health Scorecard
Financial health of major projects
| Project | BL | Contract | Billed | Collected | Unbilled | Delay Days | Est. Margin | Cash Risk | Margin Risk | Approval | Notes |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Airport DAS Expansion | Neutral Host | 185 | 120 | 98 | 25 | 45 | 24.5% | Medium | Low | Approved | Phase 2 materials on order |
| Riyadh Metro Connectivity | EPC Contracting | 420 | 310 | 245 | 55 | 68 | 18.2% | High | Medium | Escalated | Collection delay escalated to sponsor |
| AI DC Cluster Rollout | Data Center | 280 | 95 | 82 | 45 | 22 | 38.5% | Low | Low | Approved | GPU procurement on schedule |
| Smart Campus Program | Managed Services | 145 | 88 | 72 | 18 | 35 | 32% | Medium | Low | Approved | IoT phase completing Q2 |
| Fiber O&M Managed Contract | Managed Services | 95 | 62 | 58 | 12 | 15 | 35.8% | Low | Low | Approved | Recurring 5-year contract |
| NEOM Industrial Zone DAS | Neutral Host | 320 | 85 | 60 | 40 | 52 | 20.1% | High | High | Pending | Scope change under negotiation |